A shady shot. At least, this scene is devoid of Our Builder's Construction Crap. It will be so until the end of August. Our unwanted August hiatus. Yet, A Healthy Financial Blow for Our Builder...
he is obligated by Our 3rd Contract to pay Euro 75 for every day late after the June 30th Deadline. So far, he is 26 days late. He told me the other day that Phase III... Upstairs Apartment, Laundry Room & Plumbing System... won't be completed until September 15th. The Math will then say... Euro 75 x 77 days late = a bunch of Euros!!! It'll be a whole shit-load of $$$s!!! Sorry to be so vulgar, but really. Had Our Builder thrown his entire six-man squad at the three tasks of Phase III... a simultaneous assault both above & below... he could have knocked off with... I'm done Dad!!!... two weeks before the Deadline. Didn't happen that way. Now, he pays. And, I cannot figure it.
The month long Peace & Quiet may, actually, be a boon to My Tired & Stressed Spirit/Anima/Well-being/etc. I can now cat-nap/read/putter/gaze-up-into-a-cloudless-sky!!! on the terrace in front of the Upstairs Apartment without being bothered.... da nessuno. The only disturbance might be an occasional persimmon dropping from its tree bonking The Dog forcing him to move over by the pomegranate bush. No problem for me. I wear a hat. What an exciting month we are in store for!!! Gads.
No comments:
Post a Comment